- Open the column using wrenches, gently
- Replace frits every ~5x or whenever the column runs at high pressure
- Wash out with water, using a wash bottle
- Reassemble half the column, first placing the metal ring on the plastic piece, and then the larger metal piece. It should be tightened, but not super tight
- Screw on the white funnel on top and the syringe on the bottom.
- The R2 resin* is in acetonitrile. Add it to the funnel and use the syringe to pull it through. When liquid enters the syringe, it’s probably packed.
- Reassemble the column the rest of the way: metal ring, fret, large metal piece.
*R2 resin: Thermo Scientific POROS™ 20 R2 Reversed - Phase Resin
- New member onboarding
- Lab jobs
- Seminar schedules
- How to order
- Group meeting schedule
- Lab notebooks
- Funding opportunities
- Philosophy of science
- Wet lab basics
- Lab safety
- Waste disposal
- Chemical inventory
- -20C inventory
- Molecular biology
- Buffers and reagents
- Protocols library
- DNA synthesis and primers
- 80C freezer organization
- Using server
- C2B2 HPC access
- Update lab website
- Cluster parallel processing
- Mercury at CUIMC
- Getting started with Rosetta
- Install Pyrosetta
- Tutorials
- Clone Github
- Gromacs-Tutorial
- Cluster Specs
- Deep MSA and Statistical Coupling Analysis
- MMseqs2: Make MSA and analyze taxonomy
- Useful tools