part of WP1: information needed to run project management in openetcs, e.g.,
- quality assurance plan,
- scrum meeting minutes
- Full Project Proposal (FPP)
- Project Cooperation Agreement --> currently poart of management repository
Documents under Review
- QA Plan in its 0.9.5.3 version
- State of the document: review cycle finished, changes pending to be implemented.
- Branch for the review: RC_QAPlan_01 branch
- Related issue: openETCS#4
- Review process in its 0.3 version
- State of the document: the review is ongoing, the deadline is the 10th of May
- Branch for the review: RC_ReviewProcess_01 branch
- Issue: openETCS#8