Waku Project Management

Teams

The Waku Team is comprised of the following subteams:

  • Waku Research
  • Waku Development nwaku, js-waku, go-waku
  • Waku Chat

The Waku Team also gets the support from other Logos groups, in particular:

  • VAC/DST: Distributed System Testing Team for simulations and QA/Testing
  • Comms Hub: For communications, marketing, digital content, etc.

Work Tracking and Project Management Process

See PROCESS.md

Reporting Guidelines

Requirements

Weekly Reporting

Weekly reporting provides an insight on the progress by milestones.

Reporting

Weekly Updates:

Report progress on each active Deliverables per sub-team.

Every week, all team members must add their update in the appropriate discord thread WITH LINKS to the GitHub issues (not pull requests) they own and worked on over the past week and/or plan to work on next week.

If work is done on several Tasks related to the same Epic, team members are free to link the common parent Epic issue.

Please include an update for the following categories:

  • achieved: what was achieved this week.
  • next: what will be worked on next.
  • blocked: blocking items, not required if no blockers exist.

PM compiles the updates following sign-off from sub-team Leads and publishes to https://roadmap.logos.co.

Process Flow

Submit Updates (Everyone) - Tuesday
         │
         ▼
Review/Signoff (Leads) - Wednesday
         │
         ▼
Compile (PM) - Thursday
         │
         ▼
Publish (PM) - Monday

Milestones

https://github.com/waku-org/pm/milestones