(Obsolete) SB Lern - Release 5.1 #34
Replies: 2 comments
-
The Lern team has been occupied with interrupts to support the CSP related Sunbird changes for most of 5.1 Sprint 01. This has taken a significant chunk of time, and the scope of 5.1 has been revised in order to ensure that the items that are being taken up can be completed. The roadmap now has the revised (reduced) list of items for 5.1 : https://lern.sunbird.org/learn/product-roadmap The following items have been descoped from the earlier plan for release 5.1: Project: Enabling ease of adoption Project: Enabling ease of adoption Project: Enabling ease of adoption Project: Internal BB process formulation Project: Enabling ease of adoption |
Beta Was this translation helpful? Give feedback.
-
The Lern team has been occupied over Sept & Oct '2022 with CSP related changes for the Lern Building Block. |
Beta Was this translation helpful? Give feedback.
-
The details of the items planned for Release 5.1 of SB Lern have been published on the Lern microsite.
The 'Product Roadmap' page has the list of the items : https://lern.sunbird.org/learn/product-roadmap
The team will use this thread to call out any updates/ changes in plan to release 5.1
The revised dates for 5.1 are as follows:
Activity | From | To | Duration
Release Planning | 01 Aug '22 | 12 Aug '22 || 2 weeks
Design Discussions | 15 Aug '22 | 26 Aug '22 || 2 weeks
Sprint 01 | 29 Aug '22 | 16 Sep '22 || 3 weeks
Sprint 02 | 19 Sep '22 | 07 Oct '22 || 3 weeks
Regression Testing & Release | 10 Oct '22 | 04 Nov '22 || 4 weeks
Production Release 04 Nov '22
Bug Fixing & Support | 07 Nov '22 | 11 Nov' 22 || 1 week
Beta Was this translation helpful? Give feedback.
All reactions