Activity Network DiagramHere is a very rough Activity Network Diagram I put together from the Interrelationship Digraph: I'm still trying to figure out how to add start dates and end dates to the Gantt Chart in GitHub. From this I will create new Milestones that we can add tasks to so that they can be visualised on the github project board. |
Beta Was this translation helpful? Give feedback.
-
I've filled out the new milestones and potential deadlines working backwards:
Assumed start date is 27th of March. Here is an example for my responsibilities: I've tried to roughly indicate dependencies based on the start and end date. @andrearosasco, @StefanoBerti feel free to adjust your tasks accordingly. |
Beta Was this translation helpful? Give feedback.
-
Attendees:
Overview:
We ran a follow-up workshop to the previous one (#9) to determine task dependencies and priorities.
Outcomes:
Due to time constraints, we only ran the first two tasks:
Interrelationship Digraph:
Prioritization Matrix
Below are the tallies of each of the tasks labelled
Performance Driver
in descending order:Next Steps:
Beta Was this translation helpful? Give feedback.